A Written Scheme of Examination (WSE) is the legal document that must exist before a qualifying pressure system can be operated in the UK.

It sets out the parts of a system that must be examined, the method of examination, and the maximum interval permitted before the next inspection – drawn up and certified by a “competent person” as required under the Pressure Systems Safety Regulations 2000 (PSSR). Supplementary to the WSE, an APEA should be carried out on the entirety of the system, regardless of age, to ensure that each component or service is suitable for it’s intended operation. The results of this assessment can impact the frequency or type of inspection carried out against the WSE. To fulfil other obligations under PUWER, an inspection and maintenance programme should also be created and carried out periodically, giving the Owner/User a fully compliant system.

PSSR compliance matters

The Pressure Systems Safety Regulations 2000 exist because stored energy in a pressure system; whether compressed gas, steam, or a gas dissolved under pressure such as acetylene, can fail violently if a vessel, pipeline or protective device deteriorates undetected.

PSSR is enforced by the Health and Safety Executive, and non-compliance carries real consequences: improvement or prohibition notices, unlimited fines, prosecution, and in many cases invalidated insurance cover. Under Regulation 8 of PSSR, the user of an installed system, or the owner of a mobile one, is prohibited from operating it, or allowing it to be operated, unless a Written Scheme of Examination is in place. This applies before first use, regardless of how new the equipment is, and continues to apply for the operational life of the system.

Scheme of
Examination

When a Written Scheme of Examination is required, and what it covers

As a general guide, a WSE is required wherever a system holds a “relevant fluid”, compressed or liquefied gas, including air, at more than 0.5 bar above atmospheric pressure; steam at any pressure; pressurised hot water above 110°C; or a gas dissolved under pressure, such as acetylene.

In practice, this brings a wide range of equipment into scope including pressurised process gas and liquid delivery systems found across semiconductor, pharmaceutical and clean energy facilities. These are exactly the systems Orbital designs, fabricates and installs, which is why WSE sits naturally alongside our wider engineering work rather than as a separate, disconnected service.

What a Written Scheme of Examination includes

A properly drawn-up WSE identifies the parts of the system that could give rise to danger if a defect went undetected – vessels, pipelines and pipework, and protective devices such as safety valves, pressure switches and level indicators, and defines the safe operating limits of each.

It specifies the nature of the examination required for every item, the method by which it will be carried out, and the maximum interval permitted before the next examination, typically every 12 to 24 months depending on the system and its risk classification of minor, intermediate or major. The scheme itself is also subject to periodic review by the competent person, who must confirm it remains suitable as the system, its use, or its operating environment changes, for example following a modification, a repair, or the addition of a new gas line.

Orbital's Written Scheme of Examination service

For Orbital, WSE and pressure system examination isn’t a bolt-on service, it’s a natural extension of the documentation and testing discipline that already runs through everything we install.

Where Orbital has installed the system, our impartial inspectors carry out an assessment, draw up the written scheme, and schedule the examination at the correct interval, with annual inspections and scheme updates as your system changes. Where a system was installed by a third party, we can assess it independently and produce or take over WSE documentation regardless of who built it, giving you a single point of contact for compliance across a mixed estate. Every examination is followed by a clear written report and certificate, so you have the audit trail an HSE inspector, insurer or auditor will ask to see.

Industries we support

This service runs alongside the same sectors Orbital’s wider business serves:

Semiconductor manufacturers

Pharmaceutical Sites

Clean energy and hydrogen facilities,

Research and academic institutions

In each case, the requirement is the same, a defensible, up-to-date written scheme and an inspection record that holds up to scrutiny.

Frequently asked questions

What is a Written Scheme of Examination?
A Written Scheme of Examination (WSE) is a legal document required before a qualifying pressure system can be used in the UK. It identifies the parts of the system that need periodic examination, the method of examination, and the maximum interval before the next inspection, and must be drawn up or certified by a competent person.
Yes. Under Regulation 8 of the Pressure Systems Safety Regulations 2000 (PSSR), the user or owner of a qualifying pressure system must not operate it, or allow it to be operated, without a written scheme of examination in place, this applies before first use, regardless of how new the equipment is.
How often does a pressure system need to be examined?
The interval is set out in the written scheme itself and depends on the system and its risk classification, but most systems are examined every 12 to 24 months. The scheme is also periodically reviewed by the competent person to confirm it remains suitable.
What equipment needs a Written Scheme of Examination?
Broadly, any system holding a relevant fluid, compressed or liquefied gas above 0.5 bar, steam at any pressure, pressurised hot water above 110°C, or a gas dissolved under pressure such as acetylene. A common guide is systems above 250 bar litres (working pressure x volume), though steam systems are in scope at any size.
Who can produce or certify a Written Scheme of Examination?
Only a “competent person”, someone independent of the system’s operation with the relevant training, skills, experience and knowledge, and the authority to stop the system’s use if necessary. Larger or higher-risk systems typically require certification by an Incorporated or Chartered engineer.
Can Orbital provide a WSE for a system it didn't install?
Yes. Orbital’s PressureSafe-qualified engineers can independently assess pressure systems installed by third parties and produce or take over Written Scheme of Examination documentation, regardless of who originally built the system.
What happens if I don't have a Written Scheme of Examination?
Operating a qualifying pressure system without a WSE is a breach of PSSR, enforced by the Health and Safety Executive. Consequences can include improvement or prohibition notices, unlimited fines, prosecution, and invalidated insurance cover in the event of an incident.