Orbital’s biggest project to date involved the installation of high-purity gas lines for inert, toxic, flammable and pyrophoric gases for semiconductor process tools.
- £100m 18,600m2 facility
- New manufacturing facility (cleanrooms) for semiconductor process tools
- Installation of high purity gas lines for Inert, toxic, flammable and pyrophoric gases
- Started 2023 £14 million to date
- Orbital designed and manufactured point of use hardware
- 4 – 16 operatives on site, dependent on programme stage
- Orbital welding of tube sizes ¼” OD to 4” OD
- Over 30,000m of pipework installed